If you need to move, extend, remove, replace or protect our pipes and assets for your development, including temporary replacement pipes, you and your providers must get approval and enter into a Developer Works Deed with us.
Entering into the Developer Works Deed is part of the process to get approval to move, extend, remove, replace or protect any Sydney Water pipes, including temporary replacement pipes.
You must engage a water servicing coordinator to lodge an approval application with us. This includes completing all our developer deed schedules, below.
You'll need to include a design of the proposed works and any temporary pipework. We'll review the design and tell you what you need to do to get our approval. This might include lodging a construction bond.
Your complete guide
The Land development guide outlines how to meet our requirements for servicing the development and receive your Section 73 Certificate through our 'Managing New Development' process. It details the process, related policies, forms, fees and charges.
For all developments affecting any of our pipes
Find out more from our Asset adjustment and protection manual.
If you need to move, extend, remove, replace or protect and of our pipes and assets for your development, you and the listed providers you use must enter into a Developer Works Deed with us.
You and your providers must sign the Developer Works Deed before you submit the design of works.
If you haven't engaged your constructor by the time you submit the design, the deed must still be submitted with all the other signatures so we can execute it. However, your constructor must sign the Schedule 3: Deed Poll before construction begins.
Schedule 1: Standard terms
Find all Developer Works Deed conditions in the Schedule 1: Standard Terms document.
Schedule 2: Novation Deed
If you need to transfer ownership of the development site after you've signed the Developer Works Deed, complete the Schedule 2: Novation Deed.
Schedule 3: Deed Poll
Before construction can begin, your constructor must sign Schedule 3: Deed Poll.