Policy document number: DD_047476 Version: 3 Last updated: 3 February 2021
We may fence our stormwater channels to reduce safety risks to the public.
Our policy covers safety fencing, common boundary fencing and road and bridge fencing of our stormwater channels.
We may fence:
Our policy explains the minimum standards to be used when you, or we, are required to install or replace fencing around our stormwater network.
It also includes guidelines for:
We provide fencing, and/or contribute to the cost of fencing, of stormwater structures under our control to reduce any possible safety risks to the public.
We may contribute to the cost of fences that are along the boundary between private property and our stormwater asset or land. This contribution will be based on an appropriate, standard fence that is typical for the surrounding area. Our commitment will generally follow the Dividing Fences Act, noting that we are not legally bound by the provisions of this Act.
We'll contribute to half the costs of providing safety fencing within private property where the channel poses a safety risk to the occupants of the property.
We'll provide safety fencing along our open concrete stormwater channels and across headwalls where these structures are accessible by the public. We won't provide fencing where the channel is covered and doesn't represent a safety risk to the public.
We may provide safety fencing around Stormwater Quality Improvement Devices (SQIDS) and other stormwater structures where they pose a safety risk. Where we've previously installed safety fencing, or such fencing has been transferred to us, we'll generally maintain the same standard of fencing.
Where the banks of our stormwater lands are not steep and access/exit is not difficult, we generally won't fence the area. This is typical of stormwater lands in the Rouse Hill development area. We also won't install fencing that may obstruct the flow of stormwater in high rainfall events.
We may install security fencing around some of our stormwater assets, such as drainage pumping stations and open SQIDs, where required to more effectively manage safety and security issues. Security or safety fencing around Sydney Water land containing a covered stormwater channel Generally, we won't fence land around covered stormwater channels, unless there's an unacceptable safety risk. If the land is being used for unlawful purposes, such as illegal dumping of rubbish, then we may fence the site.
We'll maintain safety fences where we own the bridge, or the headwall and it poses a safety risk.
Generally, road barriers are the responsibility of local councils. However, if there's a high risk of vehicle damage to our stormwater assets, we'll install road barriers to protect our assets. We're responsible for determining where road barriers are required to protect our assets.
A minimum 1.8 m height security-type fence is required at these sites.
If your property shares the boundary of our land that has a stormwater asset, we'll install fencing if there's a safety concern. Standard common boundary contributions would apply.
We don't specify the type of common boundary fencing and will only contribute towards half the cost of a standard fence. That is, a hardwood paling or colour bond fence between 1.2 m and 1.8 m high, depending on what is typical for the surrounding area.
You'll need our consent before beginning any fencing work if we are to contribute towards the cost of replacing or repairing common boundary fencing or modifying the existing location of the fence.
Safety fencing for pedestrian and road bridges should comply with Australian Standards (AS 5100.1-2004 – Bridge Design Part 1: Scope and general principles). The minimum height is to be 1.2 m.
Where barriers are used to prevent the risk of a vehicle crashing into our stormwater asset, they must comply with Australian Standards (AS5100. 1-2004 – Bridge Design Part 1: Scope and general principles). The minimum heights should be as per standard.
All installation is to be done according to all relevant codes and regulations, including but not limited to AS 1926 - Fences and Gates for Private Swimming Pools, AS 5100.1-2004 – Bridge Design.
New or replacement gates in public areas or on our land must comply with AS 1926, Fences and Gates for Private Swimming Pools, and be of a suitable corrosion resistant material. New gates are to be placed only at locations that are above step irons in open channels.
Gates are not permitted on common boundary fencing where the boundary is next to an open stormwater channel. Any gate installed without our knowledge or consent is at the adjoining owner's own risk. We may ask the adjoining owner to remove the gate or secure the opening to prevent unapproved entry onto our land. Where a stormwater channel traverses private property and access is required over channel, we may permit a gate to access an approved bridge over an open stormwater channel.
All our gates around open stormwater channels must be secured with a Standard Jackson Lock or approved master key padlock and chain where necessary.
We're responsible for managing trees on our land and will replace fences if damaged by those trees. If a tree on private property damages a common boundary fence, then you as the owner are responsible for repairing the fence.
We'll repair our safety fencing if scouring destabilises the fence. We'll organise to restore and stabilise the land before fencing is repaired.
It's your responsibility to contact your insurer and let us know about any damage to common boundary fencing caused by flooding, falling trees, etc.
| Term | Definition |
|---|---|
Act | The Sydney Water Act, 1994 and any regulations in force under it. |
Channel | Stormwater channel owned by Sydney Water. |
Open stormwater channel | Stormwater with no covering. |
Covered stormwater channel | Enclosed channel – not open. |
Sydney Water bridge | A bridge owned by us. Can be a road bridge or foot bridge. |
Common boundary fence | Fence between private propertfy and Sydney Water land or along the edge of an easement in Sydney's Water favour. The fence can also be between private property and drainage reserves or Council easements where there is a Sydney Water asset. |
Trunk drainage land | Land set aside for drainage purposes. |
Security Fencing | Generally, a 1.8m chain wire fence with barbed wire, or another fencing designed specifically for increased site security. Determined to be required through a site safety and security Hazard Identification and Risk Assessment (HIDRA). |
SQIDS | Stormwater Quality Improvement Devices. |