Policy document number: 3064045 Version: 3 Last updated: 17 June 2026
Our policy explains to developers (you) how we apply infrastructure contributions on development applications.
Infrastructure contributions help recover the cost of providing infrastructure to new developments. As the population grows and development spreads into new areas, this requires us to build and operate new infrastructure. We also incur additional costs as we expand our existing network to service increased density in established areas.
We work out your infrastructure contribution using a method set by the NSW Independent Pricing and Regulatory Tribunal (IPART).
Our policy applies to you if you need a section 73 compliance certificate from us.
Infrastructure contributions are levied to meet statutory and IPART requirements.
We'll include an estimate of your infrastructure contribution in your Notice of Requirements. For Sydney Water Complying Applications, we'll give you a letter with your infrastructure contributions along with your invoice. Your infrastructure contribution includes a charge (2.1.1) and may be reduced by a credit (2.1.2).
We determine the charge by applying the price for one Equivalent Tenement (ET) from our Development Servicing Plans. One ET is the annual total demand of an average detached, single residential dwelling. We calculate your charge based on how many ET your development represents. The price for an ET can vary by service and location.
We work out your charge as follows:
| Service | Development type | How we calculate the charge |
|---|---|---|
Drinking water Wastewater Recycled water | Residential | We work out the number of ETs on your development based on the density of your development. A detached dwelling is typically one ET, while medium to high density developments are less than one ET per dwelling. We multiply the number of ETs by the price for one ET from the relevant Development Servicing Plan. |
Drinking water Wastewater Recycled water | Other (non-residential) | We work out how many ETs your development flow rate represents and multiply this by price for one ET from the relevant Development Servicing Plan. |
Stormwater | Rouse Hill and Mamre Road Precinct | We distribute the total value of the expected ETs for the Development Servicing Plan evenly across the net developable hectares covered by the plan, to give a rate per net developable hectare. We then multiply that rate by the number of net developable hectares in your development. |
Stormwater | Aerotropolis | We distribute the total value of the expected ETs for the Development Servicing Plan evenly across the net developable hectares covered by the plan, to give a rate per net developable hectare. We then multiply that rate by the number of net developable hectares in your development. These charges are on exhibition, and you’ll be required to bond the works for the infrastructure contributions applicable to your development. |
We may apply a credit to recognise existing usage. If the credit exceeds the charge, then a zero contribution applies, and we do not provide payment.
You must pay the infrastructure contribution once you are ready to connect to our systems. This means the works (if any) we require you to deliver on your development are complete, and your Water Servicing Coordinator has submitted all project completion packages to us. For Sydney Water Complying Applications, your Water Servicing Coordinator must have submitted a complete application to us. You can find more information about our process in our Land Development Guide.
You must pay your infrastructure contribution directly to us in accordance with the invoice issued by us. Your Water Servicing Coordinator will provide you with this invoice.
Once you've paid the infrastructure contribution (and met all other Notice of Requirements conditions), we'll issue you with the section 73 compliance certificate.
If you have met all Notice of Requirement conditions in your control and you are waiting for us to deliver dependent works, you can pay your infrastructure contribution.
If you give us an early release compliance certificate bond, your infrastructure contribution reflects when you've completed the necessary works to enable a connection. See our bonding of works policy for details. We are unable to offset the amount you pay for your infrastructure contribution against any amount we reimburse for works you are required to deliver for your development. Any reimbursements will be a separate transaction.
The infrastructure contribution you pay may be different from the Notice of Requirements estimate if:
You can contact your Water Servicing Coordinator for advice about infrastructure contributions or visit land development for more information.
If you want to dispute the method used to calculate the infrastructure contribution and this was not resolved through your Water Servicing Coordinator, you can ask us to review the calculation method. You must write a letter requesting the review, the basis of the claim and provide this to your Water Servicing Coordinator who will give it to us.
For non-residential usage disputes, your dispute must be supported by a hydraulic assessment. If your calculation method dispute is still not resolved, you have the right to have your dispute arbitrated. See Section 31 of the Independent Pricing and Regulatory Tribunal Act 1992.
The NSW Government approved the following transition pathway for drinking water and wastewater infrastructure contributions:
The NSW Government approved the following transition pathway for stormwater contributions:
There are no transitional arrangements for recycled water.
All our prices increase by the Consumer Price Index each financial year.
| Term | Definition | Source |
|---|---|---|
Net developable hectares | The area of land in hectares covered in the development consent and used in the calculation of stormwater infrastructure contributions. The exact definition will be in the applicable Development Servicing Plan. |
|
Development | Any activity relating to land that needs approval as specified under Section 69 of the Act. | Sydney Water Act 1994 |
Development Servicing Plan | A document that contains information used to calculate the infrastructure contribution. See Section 4.3 for a list. | IPART Determination |
Early release compliance certificate bond | Bonding arrangements with us for the early release of compliance certificates prior to completing works. |
|
Equivalent Tenement (ET) | The annual total demand of an average detached, single residential dwelling. | IPART Determination |
Infrastructure contribution | A contribution towards the cost of systems which serve a development. We calculate them using prices that IPART has registered. We cannot waive or change these contributions. Also known as developer charges. | Sydney Water |
Charge | Part of the infrastructure contribution calculation. Total ETs in the new development multiplied by the price for one ET from the relevant Development Servicing Plan. | Sydney Water |
Credit | May form part of the infrastructure contribution calculation. ETs of the existing property multiplied by the price for one ET from the relevant Development Servicing Plan. To determine ETs, we look at:
| Sydney Water |
IPART | The Independent Pricing and Regulatory Tribunal of NSW (IPART) is constituted by the Independent Pricing and Regulatory Tribunal Act 1992. The independent body that oversees regulation in water, gas, electricity and public transport industries in NSW. |
|
Notice of Requirements | Outlines any requirements or works you need to complete before we can issue your section 73 compliance certificate. For example, you might need to:
| Sydney Water |
Project completion package | Final documents that must be submitted to us as listed in the relevant provider instructions. |
|
Service | A service provided by us. Services include drinking water, wastewater, recycled water and stormwater. | Sydney Water |
Section 73 compliance certificate | A certificate issued under section 73 of the Sydney Water Act 1994. |
|
Sydney Water Complying Applications | Applications for a section 73 compliance certificate that only require minor works. Your Water Servicing Coordinator or Sydney Water Developer Direct can advise if your application is a Sydney Water Complying Application. | Sydney Water |
Sydney Water Developer Direct® | Manage simple construction or protection work on minor developments to meet our requirements. |
|
Water servicing coordinator | Interface between you, us and other providers, they are part of the delivery of water, wastewater, recycled water and stormwater services for property development and infrastructure projects. |
|