Policy document number: 1260459 Version: 8 Last updated: 29 September 2025
Developers construct new mains that become part of Sydney Water's ('our') network. Sydney Water ('we') then manage and maintain these assets going forward. Generally, developers hand over smaller assets to us free of charge, but we pay for larger trunk assets. Our Growth Servicing Plan (GSP) and this policy explain exactly what we pay for.
Our policy applies to all developers who are building water, wastewater, stormwater and recycled water infrastructure needed to service urban growth. It applies equally to greenfield and brownfield areas.
Our policy doesn't apply to:
Our policy helps developers understand who pays to construct the water, wastewater, recycled water and stormwater infrastructure needed to service urban growth. View our funding infrastructure to service growth examples.
The funding of infrastructure depends on whether the works will be constructed under a commercial agreement.
If a developer wants to service land ahead of our Growth Servicing Plan (GSP), they can negotiate a commercial agreement with us. Under this agreement, the developer will be responsible for constructing the trunk infrastructure to our requirements.
The GSP outlines the circumstances where we'll pay 'reasonable and efficient' costs of this infrastructure. These principles allocate risk to the developers when they develop land 'out of sequence'. (Note: This can include a recycled water scheme where the scheme is regulated by IPART.)
Developers must follow the process outlined in the GSP to accelerate the servicing of their land 'out of sequence'. The decision to enter into a commercial agreement will always be at our discretion.
Developers will fund the design, construction and commissioning stages of infrastructure.
When the developer transfers ownership of this infrastructure to us, we'll pay the developer for infrastructure under this policy.
This includes reasonable overheads but excludes the cost of the developers share of minimum reticulation outlined below.
Our principles for funding
We have two principles, they are:
The minimum amount we'll pay
We'll pay a minimum of $5,000 for professional services and construction costs. This ensures the cost of procuring works in line with our procurement guidelines doesn't exceed the value of the reimbursement.
The allocation of professional service charges
The allocation of professional services must be set out in the Project Brief Package referred to in our procurement guidelines. This will be determined in the same way as the allocation of the design fees, unless we determine otherwise.
Our criteria for funding
Intent of 'serve other land' for wastewater mains
'Serve other land' means that a direct service is provided to a property. The property in question would have a designated section of the wastewater main from which a future connection point or extension could be made. This enables the property to be connected to our wastewater system, supporting potential development or subdivision in the future.
The 'other land' must be zoned for development and included in the wastewater catchment that is served by the main. Land designated as public open space, public recreation, is not considered as “other land”, although it may still have a connection point to our system.
“Serve other land” does not mean having a wastewater main downstream from the developer's land that will transport wastewater flows from other land upstream of the developer's land. If an upsizing above the minimum sizing is required by the Code, we will fund the upsizing component (in line with criteria 1b)), as this portion is required to accommodate the wastewater flow from the upstream catchment.
When a wastewater main is to be extended in the future, and the end of the wastewater main terminates past the boundary of the developer's land as required by the Codes, the wastewater main is not considered to “serve other land”.
Intent of 'serve other land' for water mains
'Serve other land' means the section of the mains fronting a lot zoned for development and providing metered connection(s) to the development of that property.
| Term | Definition |
|---|---|
Amplification | Where a larger main size is required to serve a development because the existing main size doesn’t meet the minimum required under the Codes. |
Applicant | Anyone who applies for approval to adjust or deviate our existing water, wastewater, recycled water and stormwater asset. |
Brownfield areas | Urban areas where Sydney Water generally already has services. |
Codes | The relevant codes of the Water Services Association of Australia, including Sydney Water editions. |
Commercial agreement | A negotiated agreement that allows a developer to accelerate the delivery of major infrastructure earlier than shown in our Growth Servicing Plan (GSP). |
Developer | A person or entity who either:
|
Development | Any activity relating to land that needs an approval as specified in Section 69 of the Sydney Water Act 1994. |
Minor service extension | A property owner seeking the extension of water-related services to an existing property to make a new connection. (IPART determinations refer to this as a 'minor service extension'). This applicant will not be a Developer or an owner whose property is already connected. The property is not identified as part of our Priority Sewerage Program. |
Greenfield areas | Generally, there are areas where we have limited or no services available. These areas are usually the subject of an overall servicing strategy for increased land use such as urban subdivision. |
GSP | Our five-year Growth Servicing Plan (shown on our website) |
Interim infrastructure | Water and wastewater infrastructure constructed on the basis that it is likely to be made redundant by the delivery of our ultimate servicing strategy before the end of its engineering life. |
Lead-in-main | This is the section of water, recycled water or wastewater main from where it connects to the existing mains system to where the minimum reticulation mains for the development starts |
Lead-out-main | This is the section of water, recycled water or wastewater main from where the minimum reticulation mains end, to the end of the main required to cater for future development |
Major infrastructure | Works associated with the construction of permanent storage reservoirs, treatment plants, pumping stations and trunk mains |
Minimum reticulation | The minimum size main required under the Codes for the height and zoning of the development only. This applies for:
|
Priority Sewerage Program | Our program for improving wastewater services to unsewered urban areas identified as environmentally sensitive. |
Project Brief Package | A package that contains (but is not limited to) the project background, scope of works, program, project cost estimate and risk assessment. |
Upsizing | The difference between the size of minimum reticulation and the size of the main required by Sydney Water. |
Urban Growth | New housing, industrial and commercial development and subdivisions. |