Current Tender

Tender 0510025449

Wiley Park Reservoir WS0249 - Roof Replacement.

  • Date advertised:
    24 July 2015
  • Closing date:
    27 August 2015
  • Demolition of existing roof and associated equipment. Supply and installation of new roof structure, roof sheeting and associated ancillary equipment. 

    Tender Closing: Thursday 27th August 2015 at 9:30am

    Contact: Peter Gray

    Contact no. 02 8849 5147

    Cost of document: $70.00 (non-refundable)

    The tender documents are available for purchase and downloading from Sydney Water''s nominated website https://tenders.nsw.gov.au/sydneywater

    Background Summary

    1. Background

    This project is for the full roof replacement and localised internal lining repairs for Wiley Park Reservoir (WS0249). The scope of work broadly comprises of the following:

    Roofing & Repair works – demolition of the existing roof structure including removal and disposal of existing roof elements and sheeting, installation of new galvanised steel roof members and installation of new aluminium roof sheeting, installation of internal ladder and platform, installation of new access hatches, equipment hatches and ventilation, as well as localised repairs of the epoxy coating as required.

    2. Mandatory Requirements

    Listed below are a list of mandatory requirements & weighting criteria which will be used by Sydney Water to determine the validity of all tender submissions provided for these projects.

    The Mandatory Criteria

    Mandatory criteria

    M1 Occupational Health and Safety (minimum requirements)

    M1.1 Past OHS Performance

    M1.2 Management System Accreditation

    M1.3 Demonstrated commitment to the CRC Construction Safety Competency Framework.

    M2 Assessed financial capability to perform the contract

    M3 Quality Management System Certification to AS/NZS ISO 9001:2000

    Weighting Evaluation Criteria

    Weighted criteria Weighting (%)

    W1 Occupational Health and Safety 20%

    W1.1 Hazard Control Plan 10%

    W1.2 Management of Risks 10%

    W2 Proposed methodology and understanding 80%

    W2.1 Program / timing 25%

    W2.2 Understanding of scope and Methodology 25%

    W2.3 Resourcing and experience 15%

    W2.4 Past Performance 15%

    TOTAL 100%