Contract details: Priority Sewerage Program Stage 3

  • Reference number
    21598
  • Class
    3
  • Private sector contractor's name and address
    Priority Sewerage Project (PSP)

    275 Appin Road, Appin NSW 2560

  • Related companies responsible for performing contractual obligations
    There is no related body corporate involved.
  • Contract award date
    19 Sep 2012
  • Contract duration
    220 weeks

    Defects period ends 28/03/2017

  • Project, goods or services to be provided under the contract
    Priority Sewerage Program Stage 3
  • Estimated amount payable to the contractor
    $713,174,464.00 GST inclusive
  • Allowable variations to estimated payment amount
    The contract contains provisions which allow Sydney Water to order and pay for variations.

    There are no provisions for cost adjustment.

  • Renegotiation provisions
    There are provisions to extend the contract at the sole discretion of Sydney Water.
  • Method of tendering and criteria for assessment (if relevant)
    Direct negotiation.

    No criteria required

  • Provisions for contractor payments for operational or maintenance services
    There are no provisions to provide operational or maintenance activities.
  • Particulars of any future transfer of significant assets to and from the agency
    Not applicable
  • Results of any cost-benefit analysis
    Not applicable
  • Components and quantum of public sector comparator
    Not applicable
  • Summary of contractor's full base case financial model
    Not applicable
  • How risk will be apportioned, if relevant
    Not applicable
  • Significant guarantees or undertakings between the parties
    Not applicable
  • Other key elements of the contract
    Not applicable
Document Listing
Contract documents Download
contract document DD_082251 pdf document