This page provides regular updates on construction activities and community notices for this project.
Construction dates are subject to change depending on weather and ground conditions. Construction hours are generally:
No work is planned for Sundays or public holidays.
Date of last update: 20 November 2008
| Start Date | Details | End Date | Related Files |
| 20/11/2008 | Pipe construction - Palymra Ave, Lethbridge Park [View details] | 24/12/2008 |
|
| 17/11/2008 | Pipe construction - Bellevue Street, Parramatta [View details] | 24/12/2008 |
|
| 20/10/2008 | Pipe construction - Powers Road, Seven Hills [View details] | 31/12/2008 |
|
| 30/09/2008 | Pipe construction – Eastern Creek, Dean Park [View details] | 30/11/2008 |
|
| 26/09/2008 | Pipe construction - Corry Court and Belmore Street, Parramatta [View details] | 30/11/2008 |
|
| 11/09/2008 | Pipeline storage site established off Hammerli Way, Shalvey. [View details] | 30/06/2009 | |
| 11/09/2008 | Pipeline storage site established in Daniels Road, Bidwell. [View details] | 30/06/2009 | |
| 01/09/2008 | Pipeline storage site established at Third Settlement Reserve, Winston Hills. [View details] | 31/12/2008 | |
| 04/07/2008 | Pipeline storage site established at Peter Van Hasselt Park, Shalvey. [View details] | 31/12/2008 | |
| 04/07/2008 | Pipeline storage site established within the former ADI site, Mount Pleasant. [View details] | 31/12/2008 | |
| 05/05/2008 | Pipeline storage site established at Parramatta Correctional Centre, Parramatta. [View details] | 31/12/2008 | |
| 15/04/2008 | Pipeline storage site established at PH Jeffrey Reserve, Parramatta. [View details] | 31/12/2008 |